The Islamabad Electric Supply Company (IESCO) has announced a power shutdown in multiple areas of Rawalpindi and other linked cities on Friday, August 07.
As per the latest post shared on X, formerly known as Twitter, IESCO has released a power outage schedule in Rawalpindi and other areas.
Dear Customers,
— Islamabad Electric Supply Company ( آئیسکو ) (@Iescoofficialpk) August 6, 2026
Date: Friday, 07 August 2026
IESCO Development work Approved Shutdown of 11 KV Feeders & 132KV Grid Stations/Transmission Lines
The scheduled shutdown will affect the following areas of Operation Circles:
1. Rawalpindi cantt
2. Jhelum
3. Chakwal
4. Attock pic.twitter.com/oUindmXUkq
The department has reasoned the electricity outage with the maintenance and construction work that will be carried out during the shutdown.
Here is the power outage schedule area-wise, released by IESCO:
IESCO Rawalpindi Cantt Operation Circle
| Feeder | Sub Division | Division | Time | Affected Areas |
| Sagri | Sagri | Rawat | 6:00 AM – 10:00 AM | DHA Homes |
| Kallar Syedan | Kallar | Rawat | 6:00 AM – 10:00 AM | Kallar Syedan |
| Morgah | Morgah | Cantt | 7:00 AM – 10:00 AM | Chiriten Colony |
| Park View | Morgah | Cantt | 7:00 AM – 10:00 AM | Morgah, Park View |
| Pindi Board | Morgah | Cantt | 7:00 AM – 10:00 AM | BISE Rawalpindi |
| Bank Road 1 | Saddar | Cantt | 6:00 AM – 8:00 AM | Barkat Plaza, Zarkoon Plaza, Singapur Plaza, Adamg Road |
IESCO Jhelum Operation Circle
| Feeder | Sub Division | Division | Time | Affected Areas |
| Chappar Sharif | Bewal | Gujar Khan | 6:00 AM – 10:30 AM | Chappar Sharif, Sui Cheemian |
| Qazian | Bhadana | Gujar Khan | 6:00 AM – 10:00 AM | Bhadana, Qazian, Jhik Qadir Bux, Maini Borgi |
IESCO Chakwal Operation Circle
| Feeder | Sub Division | Division | Time | Affected Areas |
| Jamal Wal | Ghaziabad | Chakwal | 6:00 AM – 12:00 PM | Jamal Wal |
| Mengan | Ghaziabad | Chakwal | 6:00 AM – 12:00 PM | Mengan |
| Karyala | Azhar Shaheed | Chakwal | 6:00 AM – 12:00 PM | Karyala |
| K.S.M Unit-3 | Azhar Shaheed | Chakwal | 6:00 AM – 12:00 PM | K.S.M Mills |
IESCO Attock Operation Circle
| Feeder | Sub Division | Division | Time | Affected Areas |
| Hussain Abad | Hassan Abdal | Taxila | 5:00 AM – 12:00 PM | Hussain Abad |
| Lala Zar | Hassan Abdal | Taxila | 5:00 AM – 12:00 PM | Lala Zar |
| Col Sher Khan | Hassan Abdal | Taxila | 8:00 AM – 10:00 AM | GT Road, Convent School, Ahmed Nagar, Gattia Road |
| Millat Colony | Sang Jani | Taxila | 7:00 AM – 9:00 AM | Tarnol, Millat Colony, Gulshan Colony, Ittifaq Colony |
| Industrial State Bathar | Wah Cantt | Taxila | 5:00 AM – 12:00 PM | Industrial State Bathar |
| Mushtaq Hussain | Taxila | Taxila | 6:00 AM – 10:00 AM | Faisal Iqbal Town |